The 2026 editions of Approved Documents L and F: the dates and the transitional provisions

Approved Documents L and F, 2026 editions, were published on 24 March 2026 and come into force on 24 March 2027, with transitional provisions to 24 March 2028. What that means for an application made this year, and what a specification should say about it.

The 2026 editions of Approved Document L, conservation of fuel and power, and Approved Document F, ventilation, were published on 24 March 2026 and come into force on 24 March 2027. Between those two dates the current editions apply, and an application made under them is protected by transitional provisions.

The three dates

DateWhat happens
24 March 2026The 2026 editions are published. Nothing changes for applications yet.
24 March 2027The 2026 editions come into force for ordinary domestic work. Applications made from this date are assessed against them.
24 March 2028The end of the transitional period. Work with an application made before 24 March 2027 must have commenced by this date to remain under the current standards.

What "transitional" means for a job

An application made before 24 March 2027 is assessed against the current editions, and the work stays under those standards provided it commences before 24 March 2028. A job that is designed this year, submitted this year and started next year is under the current editions throughout. A job that is submitted this year but does not start until the spring of 2028 loses that protection, and the design has to meet the new editions.

For a practice, the practical point is that the date of the application matters, and so does the date work starts. A specification issued now should say which editions it is written to and should carry the transitional provision, so that the reader of the document, in 2027, knows what it was written against.

A note, not an instruction. The right thing on the last page of a specification is a short paragraph under a plain heading: that the specification is written to the Approved Documents in force at the date of issue, that the 2026 editions come into force on 24 March 2027, and that work with an application made before that date remains under the current standards provided it commences before 24 March 2028.

The wrong thing is an internal quality-control instruction left on the issued document. "Verify before issue" tells building control that the document in their hands was not.

What a library has to do about it

The 2026 editions are a rewrite of the Part L and Part F guidance, not an amendment. A clause library written to the current editions will need a full pass against the new ones during 2027: every U-value target, every ventilation rate, every reference to a table or a section. That is why a specification library is maintained on a subscription and not sold once. A one-off purchase commits the buyer to a document that stops being current on a known date.

Until the new editions have been read in full, no figure from them should be stated in a specification. A number inferred from a summary, a press release or a filename is a number invented, and a specification that goes to building control must never carry one.

Questions

Which edition does an application made in 2026 fall under?
The editions in force at the date of the application. For ordinary domestic work that is the current editions until 24 March 2027. Work with an application made before that date remains under the current standards provided the work commences before 24 March 2028.
What should the specification say?
Which editions it is written to, and the transitional provision it relies on. A short note under a plain heading such as "Transitional provisions" does it. What it should not carry is an internal instruction to whoever wrote it: "verify before issue" on an issued document tells the reader it was not.
Will the U-value limits change?
The 2026 editions are a rewrite of the Part L and Part F guidance, and a library written to the current editions will need a full pass against the new ones during 2027, not a patch. Until the new editions are read in full, no figure from them should be stated in a specification. This site does not state any.

A specification that answers these before building control asks